The Procurement of Wind Turbines

2023/10/05 10:30


        On September 28th, National Energy Group announced the candidates for winning the bid for the procurement of wind turbines for 8 wind power project sections. The total installed capacity was 1322.8MW, and five complete machine manufacturers, including Yuanyuan Energy, CRRC Zhuzhou Institute, Jinfeng Technology, Yunda Co., Ltd., and Mingyang Intelligent, were expected to win the bid.


         Among them, the lowest bid price including tower drum is 2240 yuan/kW, and the highest bid price is 2464 yuan/kW; The lowest bid price excluding tower drum is 1350 yuan/kW, and the highest bid price is 1871 yuan/kW.


        In addition, Datang Group has announced the procurement of wind turbines for seven wind power project sections, with a total installed capacity of 737MW. Goldwind Technology, Sany Heavy Energy, CRRC Zhuzhou Institute, Dongfang Wind Power, and Yuanyuan Energy have won the bid.